Goto Section: 80.47 | 80.51 | Table of Contents
FCC 80.49
Revised as of October 1, 2006
Goto Year:2005 |
2007
Sec. 80.49 Construction and regional service requirements.
(a) Public coast stations. (1) Each VHF public coast station geographic area
licensee must notify the Commission of substantial service within its region
or service area (subpart P) within five years of the initial license grant,
and again within ten years of the initial license grant in accordance with
Sec. 1.946 of this chapter. “Substantial” service is defined as service which is
sound, favorable, and substantially above a level of mediocre service which
just might minimally warrant renewal. For site-based VHF public coast
station licensees, when a new license has been issued or additional
operating frequencies have been authorized, the licensee must notify the
Commission in accordance with Sec. 1.946 of this chapter that the station or
frequencies authorized have been placed in operation within twelve months
from the date of the grant.
(2) For LF, MF, and HF band public coast station licensees, when a new
license has been issued or additional operating frequencies have been
authorized, if the station or frequencies authorized have not been placed in
operation within twelve months from the date of grant, the authorization
becomes invalid and must be returned to the Commission for cancellation.
(3) Each AMTS coast station geographic area licensee must make a showing of
substantial service within its service area within ten years of the initial
license grant, or the authorization becomes invalid and must be returned to
the Commission for cancellation. “Substantial” service is defined as service
which is sound, favorable, and substantially above a level of mediocre
service which just might minimally warrant renewal. For site-based AMTS
coast station licensees, when a new license has been issued or additional
operating frequencies have been authorized, if the station or frequencies
authorized have not been placed in operation within two years from the date
of the grant, the authorization becomes invalid and must be returned to the
Commission for cancellation.
(b) Public fixed stations. When a new license has been issued or additional
operating frequencies have been authorized, the licensee must notify the
Commission in accordance with Sec. 1.946 of this chapter that the station or
frequencies authorized have been placed in operation within twelve months
from the date of the grant.
[ 63 FR 68955 , Dec. 14, 1998, as amended at 65 FR 77823 , Dec. 13, 2000; 67 FR 48563 , July 25, 2002]
Goto Section: 80.47 | 80.51
Goto Year: 2005 |
2007
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public