Goto Section: 74.12 | 74.14 | Table of Contents

FCC 74.13
Revised as of October 1, 2006
Goto Year:2005 | 2007
Sec.  74.13   Equipment tests.

   (a) During the process of construction of any class of radio station listed
   in this part, the permittee, without further authority of the Commission,
   may  conduct  equipment  tests for the purpose of such adjustments and
   measurements as may be necessary to assure compliance with the terms of the
   construction permit, the technical provisions of the application therefor,
   the technical requirements of this chapter, and the applicable engineering
   standards.

   (b) Equipment tests may be continued so long as the construction permit
   shall remain valid.

   (c)  The authorization for tests embodied in this section shall not be
   construed as constituting a license to operate.

   [ 38 FR 18378 , July 10, 1973]


Goto Section: 74.12 | 74.14

Goto Year: 2005 | 2007
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public