Sec. 25.210 Technical requirements for space stations in the Fixed-Satellite
Service.
(a) All space stations in the Fixed-Satellite Service used for domestic
service in the 3700–4200 MHz and 5925–6425 MHz frequency bands shall:
(1) Use orthogonal linear polarization with one of the planes defined by the
equatorial plane;
(2) Be designed so that the polarization sense of uplink transmissions is
opposite to that of downlink transmissions on the same transponder; and
(3) Shall be capable of switching polarization sense upon ground command.
(b) All space stations in the Fixed-Satellite Service in the 20/30 GHz band
shall use either orthogonal linear or orthogonal circular polarization.
Those space stations utilizing orthogonal linear polarization shall also
comply with paragraph (a) of this section.
(c) All space stations in the Fixed-Satellite Service shall have a minimum
capability to change transponder saturation flux densities by ground command
in 4 dB steps over a range of 12 dB.
(d) All space stations in the Fixed Satellite Service in the 20/30 GHz band
shall employ state-of-the-art full frequency reuse either through the use of
orthogonal polarizations within the same beam and/or through the use of
spatially independent beams.
(e) [Reserved]
(f) All space stations in the Fixed Satellite Service in the 3600–3700 MHz,
3700–4200 MHz, 5091–5250 MHz, 5825–5925 MHz, 5925–6425 MHz, 6425–6525 MHz,
6525–6700 MHz, 6700–7025 MHz, 10.7–10.95 GHz, 10.95–11.2 GHz, 11.2–11.45
GHz, 11.45–11.7 GHz, 11.7–12.2 GHz, 12.2–12.7 GHz, 12.75–13.15 GHz,
13.15–13.2125 GHz, 13.2125–13.25 GHz, 13.75–14.0 GHz, 14.0–14.5 GHz and
15.43–15.63 GHz bands shall employ state-of-the-art full frequency reuse
either through the use of orthogonal polarizations within the same beam
and/or the use of spatially independent beams.
(g)–(h) [Reserved]
(i) Space station antennas in the Fixed-Satellite Service must be designed
to provide a cross-polarization isolation such that the ratio of the on axis
co-polar gain to the cross-polar gain of the antenna in the assigned
frequency band shall be at least 30 dB within its primary coverage area.
(j) Space stations operated in the geostationary satellite orbit must be
maintained within 0.05 ° of their assigned orbital longitude in the east/west
direction, unless specifically authorized by the Commission to operate with
a different longitudinal tolerance, and except as provided in Section
25.283(b) (End-of-life Disposal).
(k) Antenna measurements of both co-polarized and cross-polarized
performance must be made on all antennas employed by space stations both
within the primary coverage area to facilitate coordination with other
Commission space station licensees and outside the primary coverage area to
facilitate international frequency coordination with other Administrations.
The results of such measurements shall be submitted to the Commission within
thirty days after preliminary in-orbit testing is completed.
(l) All operators of space stations shall, on June 30 of each year, file a
report with the International Bureau and the Commission's Columbia
Operations Center in Columbia, Maryland, containing the following
information current as of May 31 of that year:
(1) Status of satellite construction and anticipated launch dates, including
any major problems or delays encountered;
(2) A listing of any non-scheduled transponder outages for more than thirty
minutes and the cause(s) of such outages;
(3) A detailed description of the utilization made of each transponder on
each of the in-orbit satellites. This description should identify the total
capacity or the percentage of time each transponder is actually used for
transmission, and the amount of unused system capacity in the transponder.
This information is not required for those transponders that are sold on a
non-common carrier basis. In that case, operators should indicate the number
of transponders sold on each in-satellite orbit.
(4) Identification of any transponders not available for service or
otherwise not performing to specifications, the cause of these difficulties,
and the date any transponder was taken out of service or the malfunction
identified.
[ 58 FR 13420 , Mar. 11, 1993, as amended at 61 FR 9952 , Mar. 12, 1996; 62 FR 5931 , Feb. 10, 1997; 62 FR 61457 , Nov. 18, 1997; 68 FR 51508 , Aug. 27, 2003;
69 FR 54587 , Sept. 9, 2004; 70 FR 32256 , June 2, 2005]
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.