Sec. 101.63 Period of construction; certification of completion of construction.
(a) Each Station, except in Multichannel Video Distribution and Data
Service, Local Multipoint Distribution Services, 24 GHz Service, and the
38.6–40.0 GHz band, authorized under this part must be in operation within
18 months from the initial date of grant.
(b) For the 70 GHz, 80 GHz, and 90 GHz bands, the 12-month construction
period will commence on the date of each registration of each individual
link; adding links will not change the overall renewal period of the
license.
(c) Failure to timely begin operation means the authorization cancels
automatically.
(d) The frequencies associated with all point-to-multipoint authorizations
which have cancelled automatically or otherwise been recovered by the
Commission will again be made available for reassignment on a date and under
terms set forth by Public Notice. See Sec. 101.1331(d) for treatment of MAS
incumbent site-by-site licenses recovered in EAs.
(e) Requests for extension of time may be granted upon a showing of good
cause pursuant to Sec. 1.946(e) of this chapter.
(f) Construction of any authorized facility or frequency must be completed
by the date specified in the license as pursuant to Sec. 1.946 of this chapter.
[ 61 FR 26677 , May 28, 1996, as amended at 62 FR 23165 , Apr. 29, 1997; 63 FR 6104 , Feb. 6, 1998; 63 FR 68982 , Dec. 14, 1998; 64 FR 45893 , Aug. 23, 1999;
65 FR 17448 , Apr. 3, 2000; 65 FR 38327 , June 20, 2000; 65 FR 59357 , Oct. 5,
2000; 69 FR 3266 , Jan. 23, 2004; 69 FR 16832 , Mar. 31, 2004]
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.