Sec. 23.31 Period of construction.
Each construction permit for a radio station in the fixed public
service will specify the date of grant as the earliest date of
commencement of construction and a maximum of eight months thereafter as
the time within which construction shall be completed and the station
ready for operation, unless otherwise determined by the Commission upon
proper showing in any particular case.